DC PLUG

Click on your Ward for current and upcoming DC PLUG construction activities in your area.

 

  • WARD 1
    Ward 1: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 1 were identified by the selection process as the grid is largely underground.

  • WARD 2
    Ward 2: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 2 were identified by the selection process as the grid is largely underground.

  • WARD 3
    Ward 3: Tenleytown, Friendship Heights, American University Park
    Work Begins: May 2019
    Estimated Completion Date: Q2 2020

    Construction Activity

    Monday, June 22, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.

    Tuesday, June 23, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.
    • Overhead pole contractor to install framing and cabling for poles in the 4700 block of Chesapeake Street for connection to transformers.

    Wednesday, June 24, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.
    • Overhead pole contractor to install framing and cabling for poles in the 4700 block of Chesapeake Street for connection to transformers.

    Thursday, June 25, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.
    • Overhead pole contractor to install framing and cabling for poles in the 4700 block of Chesapeake Street for connection to transformers.

    Friday, June 26, 2020

    • Contractor will set 3-new underground transformers at locations in the 4600 block of Chesapeake Street.

    Monday, June 29, 2020

    • Contractor will continue framing manholes, pulling cables and splicing at transformer manholes at the 4600 block of Chesapeake Street.

    Tuesday, June 30, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.
    • Overhead pole contractor to install framing and cabling for poles in the 4600 block of Chesapeake Street for connection to transformers.

    Wednesday, July 1, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.
    • Overhead pole contractor to install framing and cabling for poles in the 4600 block of Chesapeake Street for connection to transformers.

    Thursday, July 2, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.
    • Overhead pole contractor to install framing and cabling for poles in the 4600 block of Chesapeake Street for connection to transformers.

    Friday, July 3, 2020

    • Contractor will continue framing manholes, pulling cables and splicing in the 4600 block of Chesapeake Street.

    *All work is weather dependent

  • WARD 4
    Feeder 15009: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

    Feeder 14900: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: December 2019
    Estimated Completion Date: TBD

    Feeder 14900 construction will coincide with the Oregon Avenue Reconstruction project. For project updates, please visit http://www.oregonavenueproject.com.

  • WARD 5
    Ward 5: Brookland, Michigan Park, Woodridge
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 6
    Ward 6: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 6 were identified by the selection process as the grid is largely underground.

  • WARD 7
    Ward 7: Benning Ridge, Fort Dupont Park, Dupont Park, Civic Betterment, Marshall Heights, Fort Davis
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 8
    Ward 8: Congress Heights, Joint Base Anacostia-Bolling, Washington Highlands, Bellevue
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.