DC PLUG

Click on your Ward for current and upcoming DC PLUG construction activities in your area.

 

  • WARD 1
    Ward 1: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 1 were identified by the selection process as the grid is largely underground.

  • WARD 2
    Ward 2: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 2 were identified by the selection process as the grid is largely underground.

  • WARD 3
    Ward 3: Tenleytown, Friendship Heights, American University Park
    Work Begins: May 2019
    Estimated Completion Date: Q2 2020

    Construction Activity

    Monday, September 21, 2020

    • Contractor will splice dead breaks and elbows at P-154 at the 4500 block of Davenport and P-26 at the 5100 block of 44th Street NW.

    Tuesday, September 22, 2020

    • Contractor will splice dead breaks and elbows at P-26 at the 5100 block of 44th Street NW.
    • Contractor will splice 200-amp elbows and hook up secondaries at:
      • P-151 at the 4800 block of 46th Street,
      • P-140 at the 4500 block of Ellicott Street, and
      • P-132 at the 4900 block of 45th Street NW.

    Wednesday, September 23, 2020

    • Contractor will splice and tag all elbows in tap hole at P-146 at the 4500 block of Ellicott Street NW.

    Thursday, September 24, 2020

    • Contractor will splice and tag all elbows at tap hole at P-121 at the 4900 block of 45th Street NW.
    • Contractor will splice elbows and hook up secondaries at:
      • P-96 at the 4400 block of Faraday Place,
      • P-80 and P-77 at the 4400 block of Garrison Street, and
      • P-62 at the 5000 block of 45th Street NW.

    Friday, September 25, 2020

    • Contractor will splice and tag all elbows at tap hole at P-111 at the 4400 block of Fessenden Street NW.
    • Contractor will splice and hook up secondaries at:
      • P-67 at the 4500 block of Garrison Street,
      • P-53 at the 5100 block of 45th Street,
      • P-47 at the 4500 block of Harrison Street, and
      • P-42 at the 4400 block of Garrison Street NW.

    Monday, September 28, 2020

    • Contractor will continue to splice dead breaks and 200-amp elbows and install Taps:
        • P-26 on the 5100 block of 44th Street NW
    • Contractor will make final connections to transformers at:
        • P-96 on the 4400 block of Faraday Place
        • P-62 on the 5000 block of 45th Street, NW
        • P-67 on the 4500 block of Garrison Street, NW

    Tuesday, September 29, 2020

    • Contractor will complete final connections to transformer at:
      • P-26 on the 5100 block of 44th Street, NW
    • Contractor will make final connections to transformers at:
      • P-53 on the 5200 block of 45th Street, NW
      • P-77 and P-80 on the 4400 block of Garrison Street, NW

    Wednesday, September 30, 2020

    • Contractor will make final connections to transformers at:
      • P-47 on the 4500 block of Harrison Street, NW
      • P-42 and P-30 on the 4400 block of Harrison Street
      • P-26 on the 5100 block of 44th Street, NW
    • Contactor will make final connections to Tap hole:
      • P-146 on the 4500 block of Ellicott Street NW

    Thursday, October 1, 2020

    • Contractor will make final connections at Tap hole at:
      • P-87 on the 4400 block of Faraday Place NW
      • P-61 on the 5000 block of 45th Street NW
      • P-76 on the 4400 block of Garrison Street NW

    Friday, October 2, 2020

        • Contractor will make final connection to Tap holes at:
          • P-121 on the 4900 block of 45th Street NW
          • P-40 on the 4400 block of Harrison Street NW
          • P-15 on the 5200 block of 44th Street, NW

    *All work is weather dependent

  • WARD 4
    Feeder 15009: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

    Feeder 14900: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: December 2019
    Estimated Completion Date: TBD

    Feeder 14900 construction will coincide with the Oregon Avenue Reconstruction project. For project updates, please visit http://www.oregonavenueproject.com.

  • WARD 5
    Ward 5: Brookland, Michigan Park, Woodridge
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 6
    Ward 6: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 6 were identified by the selection process as the grid is largely underground.

  • WARD 7
    Ward 7: Benning Ridge, Fort Dupont Park, Dupont Park, Civic Betterment, Marshall Heights, Fort Davis
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 8
    Ward 8: Congress Heights, Joint Base Anacostia-Bolling, Washington Highlands, Bellevue
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.