DC PLUG

Click on your Ward for current and upcoming DC PLUG construction activities in your area.

 

  • WARD 1
    Ward 1: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 1 were identified by the selection process as the grid is largely underground.

  • WARD 2
    Ward 2: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 2 were identified by the selection process as the grid is largely underground.

  • WARD 3
    Ward 3: Tenleytown, Friendship Heights, American University Park
    Work Begins: May 2019
    Estimated Completion Date: Q2 2020

    Construction Activity

    Monday, March 30, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 blocks Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on 4500 block of Garrison Street and intersection of 45th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Tuesday, March 31, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on 4500 block of Garrison Street and intersection of 45th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Wednesday, April 1, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on 4500 block of Garrison Street and intersection of 45th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Thursday, April 2, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on the 4400 Block Harrison Street and intersection with 44th Street NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on 4500 block of Garrison Street and intersection of 45th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Friday, April 3, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on the 4400 Block Harrison Street and intersection with 44th Street NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on 4500 block of Garrison Street and intersection of 45th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Saturday, April 4, 2020

    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.

    Monday, April 6, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on the 4400 Block Harrison Street and intersection with 44th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Tuesday, April 7, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on the 4400 Block Harrison Street and intersection with 44th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Wednesday, April 8, 2020

    • Contractor will work to complete manholes, tap holes and transformer enclosure box inspections and green area restoration in various locations.
    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on the 4400 Block Harrison Street and intersection with 44th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Thursday, April 9, 2020

    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on the 4400 Block Harrison Street and intersection with 44th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Friday, April 10, 2020

    • Contractor will work to complete PCC Pavement, sidewalk, curb and gutter on the 4400 & 4500 Block Harrison Street and the intersection of Harrison and 45th Streets NW.
    • Contractor will work to complete PCC Pavement, sidewalk, Curb and gutter on the 4400 Block Harrison Street and intersection with 44th Street NW.
    • Contractor will work to complete asphalt restoration on Harrison, Garrison, Faraday and 45th Streets NW, and complete patch work on 46th and 45th Streets (south of River Road NW).
    • Contractor will work to complete cross walk markings in various locations.

    Saturday, April 11, 2020

    • Work TBD

    *All work is weather dependent

    Duct bank: Duct banks are groups of conduits designed to protect and consolidate cabling to and from buildings which are surrounded by a protective casing (either concrete or metal).

    Taphole: Smaller manhole (3x3x3)

    Transformer Enclosure: These enclosures are designed to provide a degree of protection to personnel against access to hazardous parts and to provide a degree of protection to the transformer from     contaminants such as moisture, dust, metallic dust, and chemicals.

    PCC Base: Base and subbase thickness for early roads. Portland cement concrete (PCC) was originally used as a base and was surfaced with wooden blocks, bricks, and cobblestones.

     

  • WARD 4
    Feeder 15009: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

    Feeder 14900: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: December 2019
    Estimated Completion Date: TBD

    Feeder 14900 construction will coincide with the Oregon Avenue Reconstruction project. For project updates, please visit http://www.oregonavenueproject.com.

  • WARD 5
    Ward 5: Brookland, Michigan Park, Woodridge
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 6
    Ward 6: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 6 were identified by the selection process as the grid is largely underground.

  • WARD 7
    Ward 7: Benning Ridge, Fort Dupont Park, Dupont Park, Civic Betterment, Marshall Heights, Fort Davis
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 8
    Ward 8: Congress Heights, Joint Base Anacostia-Bolling, Washington Highlands, Bellevue
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.