DC PLUG

Click on your Ward for current and upcoming DC PLUG construction activities in your area.

 

  • WARD 1
    Ward 1: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 1 were identified by the selection process as the grid is largely underground.

  • WARD 2
    Ward 2: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 2 were identified by the selection process as the grid is largely underground.

  • WARD 3
    Ward 3: Tenleytown, Friendship Heights, American University Park
    Work Begins: May 2019
    Estimated Completion Date: Q2 2020

    Construction Activity

    Monday, May 18, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4900 block of Chesapeake St.

    Tuesday, May 19, 2020

    • Contractor will continue underground cabling along 4900 block of Chesapeake St.

    Wednesday, May 20, 2020

    • Contractor will continue underground cabling along 4900 block of Chesapeake St.

    Thursday, May 21, 2020

    • Contractor will commence framing of manholes and underground cabling along 4600 block of Western Ave.

    Friday, May 22, 2020

    • Contractor will continue underground cabling along 4600 block of Western Ave.

    Monday, May 25, 2020

    • National Holiday- No work to be done.

    Tuesday, May 26, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4700 block of Chesapeake St.
    • Contractor will commence the preparation of installing the secondary risers from the poles down to the pads between 4600 and 4700 block of 49th St.

    Wednesday, May 27, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4700 block of Chesapeake St.
    • The Overhead Contractor will continue the preparation of installing the secondary risers from the poles down to the pads along the 4500 to 4700 block of Western Avenue.

    Thursday, May 28, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4700 block of Chesapeake St.
    • The Overhead Contractor will continue the preparation of installing the secondary risers from the poles down to the pads along the 4500 to 4700 block of Western Avenue.

    Friday, May 29, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4700 block of Chesapeake St.
    • The Overhead Contractor will continue the preparation of installing the secondary risers from the poles down to the pads along 4800 and 4700 block of Brandywine Street.

    Monday, June 01, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4600 block of Chesapeake St.

    Tuesday, June 02, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4600 block of Chesapeake St.

    Wednesday, June 03, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4600 block of Chesapeake St.

    Thursday, June 04, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4600 block of Chesapeake St.

    Friday, June 05, 2020

    • Contractor will commence with the framing of manholes and underground cabling along 4600 block of Chesapeake St.

    *All work is weather dependent

  • WARD 4
    Feeder 15009: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

    Feeder 14900: Hawthorne, Barnaby Woods, Chevy Chase, Friendship Heights
    Work Begins: December 2019
    Estimated Completion Date: TBD

    Feeder 14900 construction will coincide with the Oregon Avenue Reconstruction project. For project updates, please visit http://www.oregonavenueproject.com.

  • WARD 5
    Ward 5: Brookland, Michigan Park, Woodridge
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 6
    Ward 6: No Work Performed
    Work Begins: N/A
    Estimated Completion Date: N/A

    The DC PLUG initiative will selectively underground high-voltage lines that are most affected by storms and overhead-related outages. No feeders in Ward 6 were identified by the selection process as the grid is largely underground.

  • WARD 7
    Ward 7: Benning Ridge, Fort Dupont Park, Dupont Park, Civic Betterment, Marshall Heights, Fort Davis
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.

  • WARD 8
    Ward 8: Congress Heights, Joint Base Anacostia-Bolling, Washington Highlands, Bellevue
    Work Begins: TBD
    Estimated Completion Date: TBD

    At this time, no work is scheduled. Check back for future updates.